時間:2024-09-30 09:33
來源:國際電力環保
近日,據國際電力環保消息,越南南部9200萬美元的垃圾焚燒發電廠項目發布落后與計劃。
越南南部同奈省(Dong Nai Province)的一個垃圾焚燒發電廠項目于 2022 年獲得批準,價值近 2.3 萬億越南盾(9200 萬美元),但該項目的工作尚未開始,其可行性研究仍未完成,投資者尚未選定。同奈省規劃和投資廳副廳長 Phan Trung Hung Ha 表示,該項目比計劃晚了大約兩個月。
A waste-to-energy plant project, worth almost VND2.3 trillion (US$92 million) in Dong Nai Province, southern Vietnam, was approved in 2022 but work on the project has yet to start.
越南南部同奈省(Dong Nai Province)的一個垃圾焚燒發電廠項目于 2022 年獲得批準,價值近 2.3 萬億越南盾(9200 萬美元),但該項目的工作尚未開始。
A waste-to-energy plant project, worth almost VND2.3 trillion (US$92 million) in investment in Dong Nai Province, southern Vietnam, was approved in 2022 but its feasibility study remains incomplete and the investor has yet to be chosen.
越南南部同奈省的一個垃圾焚燒發電廠項目于 2022 年獲得批準,投資額近 2.3 萬億越南盾(9200 萬美元),但其可行性研究仍未完成,投資者尚未選定。
The provincial administration worked with relevant agencies on Tuesday(August 21, 2024) to address issues related to the long-running waste treatment project, located in Vinh Tan Commune of Vinh Cuu District.
省政府周二(2024年8月20日)與相關機構合作,解決與位于永久縣(Vinh Cuu District) Vinh Tan 鎮的長期廢物處理項目相關的問題。
In September 2022, authorities gave the green light to implement the Vinh Tan waste-to-energy plant project, whose developer is Le Delta JSC, under the public-private partnership format in two phases.
2022 年 9 月,當局批準以公私合作形式分兩個階段實施永新垃圾焚燒發電廠項目,該項目的開發商是 Le Delta JSC。
The project would process 800 metric tons of waste and generate 20MW of electricity per day in phase one.
該項目在第一階段將處理 800 噸廢棄物,每天產生 20MW 的電力。
Its waste treatment capacity would amount to 1,200 metric tons per day in phase two, with its electricity output reaching 30MW.
二期的垃圾處理能力將達到每天 1,200 噸,發電量將達到 30MW。
However, its feasibility study has not been done, causing the project to fall behind its schedule by about two months, said Phan Trung Hung Ha, deputy director of the provincial Department of Planning and Investment.
然而,該省規劃和投資廳副廳長 Phan Trung Hung Ha 表示,其可行性研究尚未完成,導致該項目比計劃晚了大約兩個月。
The Vinh Tan waste-to-energy plant project has hit a snag due to an incomplete environmental impact assessment, stalling the investor selection process.
由于環境影響評估不完整,Vinh Tan垃圾焚燒發電廠項目陷入困境,使投資者選擇過程停滯不前。
The Ministry of Natural Resources and Environment recently rejected the project’s environmental report, citing the need for further revisions.越南國家
越南國家自然資源和環境部最近拒絕了該項目的環境報告,理由是需要進一步修訂。
At a recent meeting, Vo Van Phi, vice-chairman of the provincial administration, emphasized the critical importance of the project and urged all stakeholders to expedite their efforts.
在最近的一次會議上,省政府副主席 Vo Van Phi 強調了該項目的極端重要性,并敦促所有利益相關者加快努力。
Phi specifically called on the project developer to revise the environmental report and resubmit it to the ministry for approval.
Phi 特別呼吁項目開發商修改環境報告并重新提交給國家環境部批準。
He also directed the provincial Departments of Natural Resources and Environment, along with the Department of Science and Technology, to assist the developer in finalizing the report by the end of next month.
他還指示省級自然資源和環境部門以及科學技術部協助開發商在下月底之前完成報告。
Phi instructed Vinh Cuu authorities to allocate the necessary budget to promptly complete the detailed planning for the project.
Phi 指示 Vinh Cuu 當局分配必要的預算,以迅速完成項目的詳細規劃。
原文如下: